VDT Development Iteration 04

Schedule

Monday, 4 December 2006 through Friday, 29 December 2006.

Ergs to allocate

For this iteration, we have the following known outages:

Alain 7 days vacation 18, 22–31 Dec
Andy 7 days conference 7–8 Dec, vacation 22–28 Dec
Tim 6 days vacation 22–31 Dec

Thus, we will work 40 out of a possible 60 person-days, which means we're at 67% capacity. From past iterations, our full-capacity target is 68 ergs. Thus, we can hope to finish about 45 ergs this iteration.